FutureStack 2026 — Risk Register

Generated by: General Chair skill Conference dates: October 15-16, 2026 | Austin Convention Center | 800 attendees Theme: AI Infrastructure Last updated: July 15, 2026


Active Risks

# Risk Likelihood Impact Area Mitigation Owner Status
R-01 Keynote speaker cancellation — One or more confirmed keynotes withdraw due to scheduling conflict or personal reasons M H Program Maintain a shortlist of 3 backup speakers with pre-negotiated availability. Require speakers to sign commitment letter with cancellation terms by Aug 31. Program Chair (Okafor) Monitoring
R-02 Sponsor revenue shortfall — Sponsorship revenue falls below $200K minimum needed to cover base costs H H Finance Diversify sponsor tiers with lower-cost options ($2K community tier). Activate backup outreach list of 15 companies. Identify $30K in discretionary budget that can be cut if needed. Sponsorship Lead (Tan) Active — revenue at 54% of target
R-03 Low registration numbers — Fewer than 600 paid registrants by Sept 15 cutoff M H Registration Launch targeted LinkedIn/email campaign in Aug. Offer group discount (5+ tickets). Partner with 3 local meetup groups for cross-promotion. Prepare reduced-capacity contingency floor plan. Marketing Lead (Chen) Monitoring — currently at 340
R-04 AV / technical failure on event day — Projector, microphone, or livestream failure disrupts sessions M H Venue / Ops Require AV vendor to provide redundant equipment for main stage. On-site AV tech required for both days. Run full tech rehearsal Oct 14. Backup laptop at each podium. Venue Chair (Reyes) Monitoring
R-05 Severe weather or travel disruption — Hurricane season or major storm impacts Austin travel in mid-October L H Logistics Monitor weather forecasts starting Oct 1. Pre-negotiate hotel cancellation flexibility. Prepare hybrid/virtual fallback for keynotes via livestream infrastructure. Travel insurance recommendation sent to all speakers. General Chair (Walsh) Monitoring
R-06 Catering / dietary incident — Food safety issue or failure to accommodate dietary restrictions causes attendee health issue L H Venue / Ops Require caterer to provide allergen documentation for every item. Separate prep stations for allergen-free meals. On-site first aid and EpiPen availability. Collect dietary requirements during registration (mandatory field). Venue Chair (Reyes) Monitoring
R-07 Sponsor payment delay — Signed sponsors delay invoice payment past Aug 15 deadline, creating cash flow gap H M Finance Net-30 payment terms in all contracts. Send invoice immediately upon signing. Escalation sequence: automated reminder (day 15), personal email (day 25), phone call (day 30), General Chair intervention (day 35). Maintain $40K operating reserve. Finance / General Chair (Walsh) Active — 2 invoices overdue
R-08 Volunteer no-shows — Fewer than 80% of recruited volunteers show up on event day M M Operations Over-recruit by 25% (target 50, recruit 63). Require confirmation 1 week prior. Assign backup roles. Brief a small paid temp staff contingency ($3K budget hold). Operations (Reyes) Monitoring
R-09 Wi-Fi network overload — Convention center Wi-Fi cannot handle 800+ concurrent devices, especially during live demos M M Venue / Tech Upgrade to dedicated conference SSID with 1 Gbps backhaul (in venue contract). Load-test with vendor in September. Provide hardwired ethernet at speaker podiums and demo stations. Venue Chair (Reyes) Monitoring
R-10 Code of Conduct incident — Harassment or misconduct reported during event L H Attendee Experience Publish CoC on website and in attendee welcome packet. Train 4 designated CoC responders. Establish private reporting channel (phone + email + in-app). Document response protocol with 30-min SLA for initial acknowledgment. General Chair (Walsh) Prepared

Risk Matrix Summary

Low Impact Medium Impact High Impact
High Likelihood — R-07 R-02
Medium Likelihood — R-08, R-09 R-01, R-03, R-04
Low Likelihood — — R-05, R-06, R-10

Risk Trend (Last 30 Days)

  • R-02 (Sponsor shortfall): Escalated from M to H likelihood after two pipeline prospects paused conversations.
  • R-07 (Payment delay): New — added after two Tier-1 sponsors missed Net-30 terms.
  • R-03 (Low registration): Stable — registration pace is slightly below plan but within historical range for this point in the cycle. Will reassess after early-bird close on Aug 1.
  • All other risks: Unchanged.